NACAP RAAF Base

McElligotts conducted this job in two parts. Firstly, working on the foundation of what would soon be the base of two tanks. The concrete base was track blasted and then stripe coated with the work being completed throughout the night where temperatures suited.

After a short break the team returned for stage 2. Two new tanks required full scaffold and containment followed by abrasive blasting on the outside shell. An epoxy zinc was applied with a a second coat of high build epoxy coating followed. This is the first time that the team have provided heat shrink containment, being well versed in a monaflex system on many other projects, this shows an additional service that can be provided where the project suits.